Step 4 · Acclimate Flooring Materials

Transport the new flooring materials into the room where they will be installed. Unpack the boxes or bundles, but do not remove the flooring from its packaging unless manufacturer instructions specify otherwise. Allow the flooring to sit undisturbed for the period recommended by the manufacturer, typically 48-72 hours, to acclimate to the ambient conditions of the room. This prevents expansion or contraction issues after installation.

Stesso home
SearchSearchBrowseBrowseMy ProjectsMy Projects
Log inLog inSign upSign up

Step 4 · Acclimate Flooring Materials

Transport the new flooring materials into the room where they will be installed. Unpack the boxes or bundles, but do not remove the flooring from its packaging unless manufacturer instructions specify otherwise. Allow the flooring to sit undisturbed for the period recommended by the manufacturer, typically 48-72 hours, to acclimate to the ambient conditions of the room. This prevents expansion or contraction issues after installation.

Videos for this step

Acclimate Laminate FlooringAcclimate Flooring and Establish Layout GuidelinesAcclimate Flooring Material

Tools and Materials

← Project

Flooring & Tiling

Step 4 of 11·14.4 hr left

Assess Existing Floor
60 minutes6 items
Remove Existing Flooring and Trim
180 minutes7 items
Prepare the Subfloor
240 minutes8 items
4
Acclimate Flooring Materials
10 minutes2 items
5
Lay Out Flooring
45 minutes2 items
6
Install First Row of Flooring
90 minutes7 items
7
Continue Laying Rows
360 minutes8 items
8
Cut Around Obstacles
120 minutes6 items
9
Install Final Row
60 minutes5 items
10
Install Transition Strips and Trim
120 minutes9 items
11
Clean Up and Final Inspection
60 minutes5 items