Step 6 · Install Ledger Board (if applicable)

Identify the house's rim joist above the desired deck height. Mark the ledger board's position, ensuring it is level and at the correct height for the deck slope. Remove siding if necessary and install flashing behind the ledger board. Secure the ledger board to the rim joist using appropriately sized lag screws or through-bolts at specified intervals, following local code requirements for spacing and type of fastener. Ensure the ledger board is level.

Stesso home
SearchSearchBrowseBrowseMy ProjectsMy Projects
Log inLog inSign upSign up

Step 6 · Install Ledger Board (if applicable)

Identify the house's rim joist above the desired deck height. Mark the ledger board's position, ensuring it is level and at the correct height for the deck slope. Remove siding if necessary and install flashing behind the ledger board. Secure the ledger board to the rim joist using appropriately sized lag screws or through-bolts at specified intervals, following local code requirements for spacing and type of fastener. Ensure the ledger board is level.

Videos for this step

Installing the Ledger BoardAttaching the Ledger BoardInstall Ledger Board and Drip Edge

Tools and Materials

← Project

Deck Construction

Step 6 of 13·71 hr left

Obtain Permits and Understand Local Codes
600 minutes2 items
Design and Plan the Deck
480 minutes4 items
Layout and Excavate Footings
720 minutes6 items
Pour Concrete Footings
480 minutes8 items
Install Post Anchors and Posts
360 minutes7 items
6
Install Ledger Board (if applicable)
360 minutes8 items
7
Install Beams
300 minutes6 items
8
Install Joists
720 minutes8 items
9
Install Decking
960 minutes7 items
10
Build and Install Railings
720 minutes9 items
11
Build and Install Stairs (if applicable)
600 minutes8 items
12
Apply Finishing Touches
360 minutes5 items
13
Final Inspection and Cleanup
240 minutes3 items