Step 3 · Layout and Excavate Footings

Using stakes and string lines, accurately lay out the perimeter of the deck and the exact positions for each footing based on your design. Use a post hole digger or auger to excavate holes for the footings. The depth of these holes must extend below the local frost line to prevent heaving. Ensure the holes are wide enough to accommodate the concrete forms and provide adequate support.

Stesso home
SearchSearchBrowseBrowseMy ProjectsMy Projects
Log inLog inSign upSign up

Step 3 · Layout and Excavate Footings

Using stakes and string lines, accurately lay out the perimeter of the deck and the exact positions for each footing based on your design. Use a post hole digger or auger to excavate holes for the footings. The depth of these holes must extend below the local frost line to prevent heaving. Ensure the holes are wide enough to accommodate the concrete forms and provide adequate support.

Videos for this step

Dig Footings and Set Anchoring HardwareMark Footing Locations and Square the DeckLayout and Digging Footings

Tools and Materials

← Project

Deck Construction

Step 3 of 13·97 hr left

Obtain Permits and Understand Local Codes
600 minutes2 items
Design and Plan the Deck
480 minutes4 items
3
Layout and Excavate Footings
720 minutes6 items
4
Pour Concrete Footings
480 minutes8 items
5
Install Post Anchors and Posts
360 minutes7 items
6
Install Ledger Board (if applicable)
360 minutes8 items
7
Install Beams
300 minutes6 items
8
Install Joists
720 minutes8 items
9
Install Decking
960 minutes7 items
10
Build and Install Railings
720 minutes9 items
11
Build and Install Stairs (if applicable)
600 minutes8 items
12
Apply Finishing Touches
360 minutes5 items
13
Final Inspection and Cleanup
240 minutes3 items