Step 8 · Backfill the Trench

Add the excavated soil back into the trench on top of the landscape fabric. Fill the trench to the original ground level. Create a slight crown or slope away from the drain path to direct surface water towards the drain inlet or the ground surface around it. Lightly compact the soil.

Stesso home
SearchSearchBrowseBrowseMy ProjectsMy Projects
Log inLog inSign upSign up

Step 8 · Backfill the Trench

Add the excavated soil back into the trench on top of the landscape fabric. Fill the trench to the original ground level. Create a slight crown or slope away from the drain path to direct surface water towards the drain inlet or the ground surface around it. Lightly compact the soil.

Videos for this step

Cover the TrenchBackfill the TrenchBackfill and Final Grade

Tools and Materials

← Project

French Drain Installation

Step 8 of 10·4 hr left

Mark the Drain Path
60 minutes4 items
Excavate the Trench
480 minutes5 items
Lay Landscape Fabric
120 minutes2 items
Add Base Gravel Layer
180 minutes3 items
Position the Perforated Pipe
60 minutes2 items
Fill with Gravel
240 minutes3 items
Wrap with Landscape Fabric
60 minutes2 items
8
Backfill the Trench
180 minutes3 items
9
Connect to Discharge Point
30 minutes2 items
10
Test the System
30 minutes1 items