Step 3 · Install the Evaporator Coil (Indoor Unit)

Install the evaporator coil inside the existing furnace or air handler, or in its own dedicated casing. Ensure proper sealing around the coil to prevent air leaks. Connect the condensate drain line to the coil's drain pan and route it to a suitable drainage point. If replacing an existing coil, ensure the new unit matches the existing system's tonnage and refrigerant type.

Stesso home
SearchSearchBrowseBrowseMy ProjectsMy Projects
Log inLog inSign upSign up

Step 3 · Install the Evaporator Coil (Indoor Unit)

Install the evaporator coil inside the existing furnace or air handler, or in its own dedicated casing. Ensure proper sealing around the coil to prevent air leaks. Connect the condensate drain line to the coil's drain pan and route it to a suitable drainage point. If replacing an existing coil, ensure the new unit matches the existing system's tonnage and refrigerant type.

Videos for this step

Install New Evaporator Coil with TXVInstall New Indoor A-Coil and Seal DuctworkInstall New Evaporator Coil

Tools and Materials

← Project

Air Conditioner Installation

Step 3 of 10·12 hr left

Prepare the Outdoor Unit Location
60 minutes4 items
Mount the Outdoor Unit
30 minutes3 items
3
Install the Evaporator Coil (Indoor Unit)
120 minutes6 items
4
Run Refrigerant Lines and Electrical Wiring
180 minutes8 items
5
Connect Electrical Power to the Outdoor Unit
90 minutes7 items
6
Evacuate and Charge Refrigerant Lines
120 minutes7 items
7
Leak Test Refrigerant Lines
45 minutes4 items
8
Connect Indoor Unit Electrical Power
60 minutes5 items
9
Perform System Startup and Testing
60 minutes4 items
10
Final Checks and Commissioning
45 minutes4 items