Step 2 · Install Gutter Hangers (Brackets)

Position the gutter hangers according to the marked slope, typically every 24 to 32 inches along the fascia board. The hangers should be aligned with the chalk lines or pencil marks indicating the top of the gutter. For seamless gutters, hangers are usually installed inside the gutter channel. For sectional gutters, they are typically screwed through the back of the gutter into the mounting surface. Ensure the hangers are securely fastened to provide adequate support for the gutter system, especially in areas with heavy rainfall or snow.

Stesso home
SearchSearchBrowseBrowseMy ProjectsMy Projects
Log inLog inSign upSign up

Step 2 · Install Gutter Hangers (Brackets)

Position the gutter hangers according to the marked slope, typically every 24 to 32 inches along the fascia board. The hangers should be aligned with the chalk lines or pencil marks indicating the top of the gutter. For seamless gutters, hangers are usually installed inside the gutter channel. For sectional gutters, they are typically screwed through the back of the gutter into the mounting surface. Ensure the hangers are securely fastened to provide adequate support for the gutter system, especially in areas with heavy rainfall or snow.

Videos for this step

Prepare Gutter HangersInstall Robust Gutter HangersInstall Gutter and Hangers

Tools and Materials

← Project

Gutter Installation

Step 2 of 7·7.9 hr left

Measure and Mark Gutter Layout
60 minutes4 items
2
Install Gutter Hangers (Brackets)
90 minutes5 items
3
Cut and Fit Gutters
120 minutes7 items
4
Mount Gutters
90 minutes5 items
5
Install Downspouts
100 minutes9 items
6
Seal All Joints and Connections
45 minutes4 items
7
Test the Gutter System
30 minutes4 items