Step 6 · Install Deck Joists

Mark the joist layout on the beams according to the plan (typically 16 inches on center). Attach joists to the beams using joist hangers or by toenailing/screwing. Ensure joists are crowned upwards (slight upward bow) to counteract deflection. Install blocking or bracing between joists as required by code to prevent twisting and add rigidity.

Stesso home
SearchSearchBrowseBrowseMy ProjectsMy Projects
Log inLog inSign upSign up

Step 6 · Install Deck Joists

Mark the joist layout on the beams according to the plan (typically 16 inches on center). Attach joists to the beams using joist hangers or by toenailing/screwing. Ensure joists are crowned upwards (slight upward bow) to counteract deflection. Install blocking or bracing between joists as required by code to prevent twisting and add rigidity.

Videos for this step

Install Joists, Bracing, and HangersInstalling Floor Joists and BlockingInstall Joists and Blocking

Tools and Materials

← Project

Decking and Railing Installation

Step 6 of 10·26 hr left

Plan and Design the Deck
360 minutes5 items
Lay Out and Excavate Footings
240 minutes5 items
Pour Concrete Footings
180 minutes7 items
Install Deck Posts
120 minutes6 items
Install Beams
180 minutes5 items
6
Install Deck Joists
300 minutes10 items
7
Install Decking Boards
480 minutes8 items
8
Build and Install Railing Posts
240 minutes6 items
9
Install Top and Bottom Rails
180 minutes6 items
10
Install Balusters or Infill
360 minutes5 items